WorkPackage Outputs/ Activities
Deadline/Dates
WP1 - Project management Begins
01/11/10
WP2- Research of training needs Begins
01/12/10
WP6 - Internal assurance of quality  Begins
01/12/10
WP7 – Dissemination – Promotion of ECHOE Begins
01/12/10
WP1 - Project management Kick-off meeting
31/12/10
WP1 - Project management Partnership agreement
31/12/10
WP1 - Project management Internal financial and reporting template
31/12/10
WP2- Research of training needs Research plan, methodology and tools
31/12/10
WP1 - Project management 1st Meeting minute
31/01/11
WP1 - Project management 1st Coordinators meeting - Bxl
31/01/11
WP6 - Internal assurance of quality  Quality plan and instruments
28/02/11
WP7 – Dissemination – Promotion of ECHOE Documents
28/02/11
WP4 – Development – ECHOE for adult learners and educators Begins
01/03/11
WP1 - Project management 1st internal report
31/03/11
WP2- Research of training needs Report on training need of adult educators
31/03/11
WP2- Research of training needs Finishes
31/03/11
WP7 – Dissemination – Promotion of ECHOE ECHOE web site
31/03/11
WP3 - ECHOE contribution to learning outcomes Begins
01/04/11
WP1 - Project management 2nd partners meeting
30/04/11
WP1 - Project management 2nd meeting minute
31/05/11
WP6 - Internal assurance of quality  1st quality report
31/05/11
WP1 - Project management 2nd internal report
31/07/11
WP5 – Exploitation – Piloting the materials Begins
01/08/11
WP7 – Dissemination – Promotion of ECHOE Project presentation fliers
31/08/11
WP3 - ECHOE contribution to learning outcomes ECHOE contribution - document guidance papers
30/09/11
WP3 - ECHOE contribution to learning outcomes Finishes
30/09/11
WP5 – Exploitation – Piloting the materials Partners exploitation meeting
30/09/11
WP8 – Dissemination – Dissemination and exploitation Begins
01/10/11
WP4 – Development – ECHOE for adult learners and educators ECHOE for adult learners and educators - Methodological papers
31/10/11
WP4 – Development – ECHOE for adult learners and educators Finishes
31/10/11
WP1 - Project management Progress report
30/11/11
WP1 - Project management 3rd internal report
30/11/11
WP5 – Exploitation – Piloting the materials Training programme and materials
30/11/11
WP6 - Internal assurance of quality  2nd quality report
30/11/11
WP1 - Project management 2nd Coordinators meeting - Bxl
31/01/12
WP1 - Project management 3rd partners meeting
28/02/12
WP1 - Project management 3rd meeting minute
31/03/12
WP1 - Project management 4th internal report
31/03/12
WP5 – Exploitation – Piloting the materials Creative traces - Documents
31/05/12
WP5 – Exploitation – Piloting the materials Finishes
31/05/12
WP5 – Exploitation – Piloting the materials Workshops with local target groups
31/05/12
WP8 – Dissemination – Dissemination and exploitation Resource book on heritage and outdoor education
30/06/12
WP1 - Project management 5th internal report
31/07/12
WP8 – Dissemination – Dissemination and exploitation Curtisoara summer school
31/07/12
WP6 - Internal assurance of quality  3rd quality report
30/10/12
WP6 - Internal assurance of quality  Finishes
30/10/12
WP7 – Dissemination – Promotion of ECHOE Finishes
30/10/12
WP8 – Dissemination – Dissemination and exploitation Articles in specialized media
30/10/12
WP8 – Dissemination – Dissemination and exploitation Finishes
30/10/12
WP1 - Project management 4th partners meeting
31/10/12
WP1 - Project management 4th meeting minute
31/10/12
WP1 - Project management Finishes
31/10/12
WP1 - Project management 6th internal report
30/11/12
WP1 - Project management Final report
31/12/12